Yes. Every new house on Prince Edward Island needs a building permit, and it also needs a development permit, which is usually approved before the building permit. The development permit covers land use: where the house sits on the lot, the well and septic, and the driveway. The building permit covers construction to the National Building Code. Outside the towns with their own planning bylaws, the province issues both.
What is the difference between a development permit and a building permit?
A development permit approves the use of the land, and a building permit approves the construction. The province's development permit guide puts it plainly: they are two different permits under two different laws. The development permit comes under the Planning Act and looks at water and sewer, road access, environmental features and where the building sits. The building permit comes under the Building Codes Act and checks the plans against the building code. The building permit is usually issued after the development permit, but both applications can go in at the same time.
Who issues the permits for a new house on PEI?
Outside a municipality with its own planning bylaws, the province issues both permits. Inside one, the town or city office issues the development permit, and the building permit depends on the town:
| Where the lot is | Development permit | Building permit |
|---|---|---|
| Outside a municipality with its own planning bylaws | The province (Lands Division) | The province |
| Inside a municipality with its own planning bylaws | The town or city office | Charlottetown, Stratford and Summerside issue their own. Elsewhere, ask the town office or the province's permit line |
The province's guide lists 29 municipalities with their own official plans and bylaws, including Summerside, Kensington, Alberton, O'Leary, Tignish, Wellington, Miscouche, Kinkora, Borden-Carleton, Victoria and Cornwall. Inside those towns, the province is still involved in the septic system and the site suitability assessment.
Provincial development permit offices are in Charlottetown (902-368-5280), Summerside (902-432-2802), O'Leary (902-859-8854) and Montague (902-838-0605). Provincial building permit applications go to the Charlottetown office at 31 Gordon Drive or to Access PEI in Summerside, O'Leary or Montague, and the building permit and inspection line is 1-800-370-3977.
Which building code applies to a new house on PEI?
The National Building Code of Canada 2020. PEI's Building Codes Regulations adopted it, along with the 2020 National Energy Code for Buildings, and the change took effect on March 31, 2024. It replaced the 2015 edition. The code applies to every dwelling, including cottages and tiny homes.
What does a building permit application need?
A complete set of plans and the approved development permit. The provincial application asks for:
- the approved development permit from the town, or the date the provincial development permit application was paid
- a site plan
- foundation plans
- floor plans
- front, side and rear elevations
- cross-sections
- truss or structural framing drawings (these must be in before the framing inspection)
- the property number (PID), the house's size, storeys, foundation, heating, siding and roofing, and the estimated value of construction
- the names of the engineer or designer, general contractor, heating contractor, electrician and plumber
The form warns that an application missing any of this is returned as incomplete.
What does a development permit application need?
The property number and lot details, how the lot will get water and sewer service, how it will be accessed, the building's setbacks and a site plan. The site plan shows the lot's dimensions and property lines, the distance from the house to the road and the lot lines, where the well and septic go, and how close the house is to any wetland, river, dune or steep bank.
Before applying, the province's guide suggests checking four things:
- Is the lot approved? A lot that has not been through subdivision approval needs that first, usually with a surveyor.
- Does the lot need a site suitability assessment? One is needed to develop a lot that will have a septic system.
- Septic paperwork: a licensed septic contractor files the sewage disposal system form.
- Are there protected features nearby? Watercourses, wetlands, buffer zones and sand dunes are protected, and the application goes to the Department of Environment for review if any are close.
How much does a building permit cost on PEI?
On the provincial schedule, a building permit for a new house up to 139 square metres (about 1,496 square feet) is $960. Each further 50 square metres adds $160, so a house of 140 to 189 square metres is $1,120. The fee covers the plan review and the required inspections. The provincial development permit for a new house is $250, and the occupancy permit is $25.
Inside the towns, fees follow the town's own schedule. Charlottetown, for example, charges $5.50 per $1,000 of construction value for a house, plus a $1,500 residential development deposit. The provincial fees are from the province's Building Codes Regulations and Charlottetown's from its schedule amended in July 2023. Fees can change, so check the current form or the town office before applying.
What other permits does a new house need?
Usually an entrance way permit for the driveway, septic registration, and separate electrical and plumbing permits:
- Driveway onto a provincial road: an entrance way permit from the Department of Transportation and Infrastructure. No new entrance can be built without approval, and a development permit can be refused if the entrance does not meet the province's sight distance standards.
- Septic system: a licensed site assessor or engineer completes the site suitability assessment, and a licensed septic contractor installs the system. Both register their forms with the province.
- Electrical and plumbing: separate permits, which the province's guide lists alongside a civic address, a driveway culvert and water testing.
How close to the shore can you build on PEI?
At least 75 feet (22.9 metres) from the top of the bank above a beach, or 60 times the annual erosion rate if that is greater. The limit is 100 feet (30.5 metres) from a migrating sand dune and 75 feet from a wetland or watercourse. The Department of Environment can require a greater distance if the standard one would not protect the beach, wetland or watercourse. These distances come from the Planning Act's subdivision and development regulations. Inside a town with its own bylaws, check the town's rules as well.
What inspections happen while the house is built?
Three at a minimum, under the Building Codes Regulations:
- Footings and foundation, before backfilling.
- Framing and building envelope, including insulation and vapour barrier, before the walls are covered.
- Final, before the work is complete.
The owner books each inspection at least three days before that stage is finished, on the province's line at 1-800-370-3977, or through the town where the town issues its own building permits. An occupancy permit is needed before anyone moves in.
Who signs the permit application?
The owner. The provincial building permit form needs the owner's signature, or the owner's written permission for someone else, such as the builder, to apply for them. The same form names the general contractor, designer and trades, so it helps to have the builder chosen before applying.
GI Adams Construction builds custom homes, cottages and additions on Prince Edward Island, from Tignish to Cornwall. To talk about a lot and a plan, get in touch for a free quote.